The keel plates were impossible to shape with our machinery.
So we had to build a wood mockup like Brian did and carry the two thick plates to another shop.
We ally could get the proper curve on the plates and position them.
Now the boat has a keel
Planning ahead: with a friend, a carpenter, we discussed on how to proceed with the woodwork when it will be time
Friday, September 23, 2011
Friday, September 16, 2011
Top Side Plates Part 2
It took a couple of days to complete the port top side plates. These plates are very long and flexible. The total length is 13.27 meters in two pieces.
After placing them side to side we checked the horizontal position with the laser level and the started welding
with the usual technique.
Before placing the plate a little detail on how the stringers connect to the centerline at the boa
And now the second plate goes in position
Tuesday, September 13, 2011
Top Side Plates
Sepetember 13, 2011
The day has come!!!
We start placing the plates.
We polished them
Welded them together
And here it is my BOWWWWW!
Thanks, many thanks to Antonio, Luciano, Pietro in strict alphabetical order!
The day has come!!!
We start placing the plates.
We polished them
Welded them together
And here it is my BOWWWWW!
Thanks, many thanks to Antonio, Luciano, Pietro in strict alphabetical order!
Monday, September 12, 2011
Intermediate Keel Floors - Stringers
September 12, 2011
We placed the intermediate keel floor and placed supports for when, later these will become the tops of the ballast
We welded the segments of stringers
We are getting closer to placing plates!!!
We placed the intermediate keel floor and placed supports for when, later these will become the tops of the ballast
We welded the segments of stringers
We are getting closer to placing plates!!!
Friday, September 9, 2011
Bathing Platform Corrections
September 9, 2011
Slow day.
We started correcting the minor error on cutting file on transom.
As I elongated the bathing platform, thie needed to be raised on the DWL and the centerlin elongated.
Also the opening in the transom had to be modified, but it wasn't.
So we have this hole that needs to be corrected. A piece of flange was removed.
Whe shall cut a piece to fill the gap
Slow day.
We started correcting the minor error on cutting file on transom.
As I elongated the bathing platform, thie needed to be raised on the DWL and the centerlin elongated.
Also the opening in the transom had to be modified, but it wasn't.
So we have this hole that needs to be corrected. A piece of flange was removed.
Whe shall cut a piece to fill the gap
Thursday, September 8, 2011
Tank Sides
September 8, 2011
In the past three days we completed the tank sides
Placed the bilge drain tube
The big tube for the forward entry of the keel
And the keel bottom
Now we have a keel
Tomorrow we will check the proper alignement again
Monday, September 5, 2011
Tank Top
September 5, 2011
Today we completed construction of the tank top, their landings (using a 30x30x4) and lids.
The landings were assembled on the linds and then welded to the tops.
Today we completed construction of the tank top, their landings (using a 30x30x4) and lids.
The landings were assembled on the linds and then welded to the tops.